PM inspects progress of Trung Luong-My Thuan Expressway

Prime Minister Nguyen Xuan Phuc on March 8 made a field trip to the Trung Luong-My Thuan Expressway in Phu Nhuan commune, Cai Lay district, the Mekong Delta province of Tien Giang.

The PM was reported that land clearance for the build-operate-transfer (BOT) project has been basically completed and 35% of the workload has been fulfilled.

As many as VND790 billion (nearly US$34 million) out of the total investment capital of nearly VND12.7 trillion (US$545 million) is expected to be disbursed in the first quarter of 2020.

PM, Trung Luong-My Thuan Expressway, field trip, build-operate-transfer, open to traffic, investment capital

PM Nguyen Xuan Phuc inspects the progress of the Trung Luong-My Thuan Expressway project in the Mekong Delta province of Tien Giang.

The 51.1 km expressway is projected to open to traffic in December this year.

PM Phuc lauded Tien Giang province – the project’s main investor, contractors and relevant agencies for their efforts in land clearance and the construction work.

To speed up the progress of the project, he asked Tien Giang to allocate the remaining investment capital promptly and closely, in line with legal regulations, while dealing with saltwater intrusion in order to facilitate the construction.

The project, together with the Ho Chi Minh City-Trung Luong and My Thuan-Can Tho expressways will contribute to connecting 13 Mekong Delta provinces and HCM City, creating a complete transport system that helps to ease traffic congestions at National Highway 1 and spur regional socio-economic development.

Free toll for Bac Giang – Lang Son expressway on Lunar New Year occasion
(BGO) – The General Director of BOT Bac Giang – Lang Giang Company Vu Minh Hoang on January 5 informed that the People’s Committee in Lang Son province agreed with the investor’s proposal to operate the expressway with free of charge during the occasion of Lunar New Year (Year of the Rat). 
 
A roadmap to construction of 11 North-South Expressway sections
Vietnam will start construction of three North-South Expressway sections this year and open bids for the remaining eight next year.
 
Government approves Tuyen Quang-Phu Tho expressway project
The Government has approved the construction of an expressway connecting the northern provinces of Tuyen Quang and Phu Tho under the Build-Operate-Transfer (BOT) format after three years of delays.
 
North-South Expressway projects receive applications from 32 investors
The management boards of the North-South Expressway’s sub-projects have received applications from 32 domestic investors and joint ventures.
 
Transnational expressway investor selection to take until August 2020
Switching from an international to a domestic tendering process for the North-South Expressway means the investor selection will take at least until August 2020 to complete.
 

Source: NDO/VNA