Test run of Saigon's first metro line slated for Q3

HCMC is expected to have the first two trains of its metro line No.1 run on a trial scheme in the third quarter.

The second train of the line, comprising three cars, was transported from Khanh Hoi Port in Ho Chi Minh City’s District 4 to Long Binh Depot in Thu Duc City on Tuesday, a day after it had arrived from Japan.

Test run, Saigon, first metro line, Q3, metro line No.1, pilot runs, entire route, zero-load trial operations

A metro car of HCMC's metro line No.1 is put onto the T1 track at the Long Binh Depot in HCMC, May 11, 2021.

The train has been installed on the T1 track where the first train had been placed last October.

Together, they will conduct pilot runs, first on small sections of the line and then on the entire stretch, which connects Ben Thanh Market in District 1 with Suoi Tien Theme Park in Thu Duc City.

The trains will first operate within the depot's precinct at the speed of 20 kph, and then on the elevated section at the designed speed of 110 kph and finally, run along the entire route in the third quarter, said Hoang Mai Tung, an engineer employed by the HCMC Management Authority for Urban Railways, the project's investor.

The two trains will have their zero-load trial operations at the depot before running with simulated passengers along the elevated section and the entire route.

The Japanese contractor, conglomerate Hitachi, will be in charge of the test run.

HCMC's first metro line will have 17 Japanese-made trains in total. The third train with three cars was also delivered to Khanh Hoi Port along with the second train and is expected to be transported to Long Binh Depot on Thursday.

Hitachi plans to deliver two more trains in June and July.

Each of the three-car trains has a capacity of 930 passengers and can travel at up to 110 kph above ground and 80 kph underground.

Work on the much-delayed line, which began in 2012, is 85 percent complete.

The city had hoped to begin commercial operations by the end of this year, but the Covid-19 outbreak has delayed it until next year.

It plans to build eight metro lines in all running a total of 220 kilometers.

Second Hanoi metro line conducts debut trial run
The first train to operate on the Nhon-Hanoi Station railway conducted a trial run Friday morning, three months after it reached Nhon Depot from France.
 
Hanoi metro test run goes ‘relatively well’: authorities
The test run of Hanoi’s first metro line has been completed, and it will be handed over to city authorities next quarter for commercial operation.
 
Hanoi's first metro line to start final 20-day test run
Hanoi’s first metro route is scheduled to commence 20-day safety evaluation in early December prior to entering commercial operation next year.
 
A glimpse into HCMC’s 1st metro line
Eight years after construction began, work on HCMC's first metro route is over 77 percent complete, with its first three-car train installed recently for an upcoming test run.
 
Hanoi's metro line to begin service in late 2021
The Nhon-Hanoi Railway Station metro line, the third metro line in Hanoi, is scheduled to begin commercial operation of the elevated section in late 2021, while the construction of the underground tracks will commence in the first quarter of 2021.
 

Source: VnExpress